Diary
Earthworks begin on lagoons. Pre Mobilisation and
fabrication begins.
November 30 After months of pre-site preparation Paul Dick Operations Manager gives the go ahead for site mobilization. Plane tickets are booked and freight arranged.
December 4+5 PMP Environmental Staff arrive on site. Materials begin to arrive. Home for Christmas minus 2 staff who left the company.
2January 2007 Second Back to WA Lining works begin on the Facultative Lagoon and both it and the smaller Reactor Lagoon are complete by 9/01/07, Connecting pipe work and valves are installed. Back to Melb 24/01/07 or Australia Day Weekend.
25February 2007 Third Tour Works begin on the Larger Anaerobic Lagoon.
June 2007 Fourth Tour Lining of Anaerobic Lagoon
July 2007 Fifth Tour Pinning down of cover Vent ports and outlet from Facultative lagoon to Evaporation pond
October Sixth Tour Works due to heavy rains
January 2008 Seventh Tour Electrical contractors
April 2008
|