PMP Environmental
   

Diary


October -November

 Earthworks begin on lagoons. Pre Mobilisation and fabrication begins.

 

November 30

After months of pre-site preparation Paul Dick Operations Manager gives the go ahead for site mobilization. Plane tickets are booked and freight arranged.

 

December 4+5

 PMP Environmental Staff arrive on site.

Materials begin to arrive.

Home for Christmas minus 2 staff who left the company.

 

2January 2007 Second
Tour

Back to WA 

Lining works begin on the Facultative Lagoon and both it and the smaller Reactor Lagoon are complete by 9/01/07, Connecting pipe work and valves are installed.

Back to Melb 24/01/07 or Australia Day Weekend.

 

25February 2007 Third Tour

Works begin on the Larger Anaerobic Lagoon.

 

June 2007 Fourth Tour

Lining of Anaerobic Lagoon

 

July 2007 Fifth Tour

Pinning down of cover

Vent ports and outlet from Facultative lagoon to Evaporation pond

 

October Sixth Tour

Works due to heavy rains

 

January 2008 Seventh Tour

Electrical contractors

 

April 2008