February 2006 Preliminaries Design and drawings Detailed designs and reviews were completed for earthworks, hydraulics, biogas collection and lagoon layout. Sketches were transformed into drawings and issued to the client. Biogas flare Contract let for the flare manufacture and design and drawings undertaken Purchasing Materials ordered and suppliers established to complete the project Factory Fabrication Custom pits and specialised fitting fabrication was undertaken under workshop conditions March 2006 Off and running, at full speed. Earthworks Contract let and works started on site with completion expected in 11days Factory Fabrication Factory Fabrication continues with materials and prefabricated items being transported to site Biogas flare Prefabrication is completed and factory testing is undertaken to prove performance. Plumbing HDPE pipe welding and pit installation commences mid month on the aerobic lagoon. Plumbing works commences on the anaerobic lagoon once the earthworks is complete in preparation for liner crew Membrane Membrane crew mobilised to site mid to late month to commence lining the anaerobic lagoon. The anaerobic pond lining was off to a flying start with 80% of the pond lined before progress was hampered by a rare rain event (26mm over night). April 2006 Just Cruising Biogas flare Flare erected and the flare shed constructed. Plumbing Distribution pipe work on the liner commenced in anticipation of the processing plant waste coming on line to fill the lagoon. Above ground pipe work and pump installation commenced. Membrane Anerobic pond liner completed, cover installation awaiting waste from the processing plant. Aerobic pond lining commenced. Personnel Matt leaves to travel overseas, Paul Dick takes over reigns as Project Manager. After 2 full weeks off site due to extended Easter-ANZAC Break full contingent of staff return to site 26 April Progress Waste flows into the anaerobic pond so cover can be commenced.(April 27) May 2006
June - July 2006 Membrane Late July all remaining membranes and machinery are demobilized off site.
August 2006 Progress Delays due to slow filling of lagoons from factories. Commissioning Final commissioning on flares completed by GASCO Pumps and electricals commissioned by Electricians. All membrane and pipe-work finished De-mobised off site. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||